The mine Alexievskaya (Kemerovo region). Commissioned the new lava

On mine "Alexievskaya", within the structure Coal company "Nina", launched a new Chapter 102/1 in reservoir "Krasnogorsky" with reserves 1 370 000 tons of coal.

The length of the new lava — 240 meters. Removable reservoir thickness — 4.1 meter. Planned daily load on the lava — 7000 tons of coal. It is expected that the monthly performance since May, will be 210000 tons of coal.

Since the beginning of 2012 to "Alexievslaya" prepared more than four kilometers of mining, production volume amounted to 512,000 tons of coal. Starting a new lava will employ mining group "Alexievslaya" to the end of the year.

By 2015, "Alexievskaya" plans to go to the line in production 5000000 tons of coal for this purpose in accordance with the new projects need to reconstruct the chain of transport companies. In the near future the main industrial area of the mine to resume construction of the previously dormant subsidiary and conveyor shafts. It is planned that in the second half of 2013 conveyor transport "Alexievslaya" will be able to take the necessary amounts of coal.

Rewiring the complex of lava 101/2 in the lava 102/1 is produced in 25 days. In the new longwall roof support 164 mounted mechanized complex KM-800, MB-712 harvester, loader, PSP-308, face conveyor ASF.