The train trestle in the Moscow City

Now experts "bridge builders" holds more than 50% of works on bored piles to support the construction of flyovers length of 638 meters.

The project is located in the Central Administrative District of Moscow, along the Third Ring Road overpass in the Moscow International Business Center "Moscow City".

The construction is a joint double-track railway pier, in the Small Ring of Moscow Railway Dorogomilovsky from the railway bridge to the end of the overpass over the direction of Smolensk. 

The works are divided into 3 sections — the builders completed the replacement of the span Dorogomilovsky bridge across the Moscow River between the legs 4 and 5, in the second portion is 40% completed demolition of the existing embankment — this is where the device ends 18-meter bored piles, in the third section completely dismantled trusses western overpass over Smolensk direction of Moscow Railways. Started assembling the new overpass, manufacture and supply of 470 tons of steel for which the MCW "bridge builders".

"The main work is done by the West overpass — Dorogomilovskaya from here to the bridge is dismantled the existing embankment. On today removed more than 45,000 cubic meters of soil. Completed device bored piles for 15 of the 29 overpass supports. 4 built props, made three beams span. Overpass will pass road thoroughfares, projected in the development of the transport infrastructure of the International Centre Moscow City ".

In parallel, work started on the removal of a large number of utilities, fully completed reconstruction of the railway networks. Building complicated constrained nature of the work — is located near Lewis Ginter Botanical Garden. Sechenov, gas distribution substation. Almost close to the project site abuts the Third Ring Road.

At the facility employs more than 270 specialists "bridge builders" — groups of SU "Spetsstroitelstvo" SMU-2, SMU-33, and a subsidiary of "RosMonolit." Issue documentation exercise planners of transport infrastructure department of Omsk association.

Completion date: March 2014. Client: Department of Civil Engineering of Moscow.

General contractor: NGO "Mostovik".