Delivered road tunnel on the 86th km of the road Kavkaz

July 12, a ceremony of putting into operation the tunnel at 86 km of the "Caucasus". Specialists Group "SK MOST" It took one and a half years to build a tunnel length of 310 m, avalanche gallery length of 63 m, a number of retaining structures and building maintenance services.

By experts Group divisions "SK MOST" in the tunnel are also made all the utilities — lighting, video surveillance, communications, burglar alarm.

Work on site began in December 2010. Breakthrough tunnel was September 1, 2011 the State Commission decided to June 29, 2012

In the works at the facility, located at km 86 +300 of the road "Kavkaz", were involved in groups — the general contractor of JSC "USK MOST", subcontractors, LLC "BPS-Gidrostroy", LLC "Mostotrest 2005" and LLC "Kapitalstroy" design organization — JSC "Minskmetroproekt" and LLC "Krasnoyarskmetroproekt."