Construction of feed mill started in the Amur region

Construction of feed mill "Amurptitseprom" worth 230 million rubles Bilohirsk started in the Amur region.

Plant for the production of animal feed will be built in the industrial zone Belogorska at the site destroyed in the 90 years the company. The maximum capacity of the new plant will be more than 57,000 tons of feed per year.

The first phase feed mill and grain elevator is scheduled for September 2014. The plant will fully meet the needs of the St. Nicholas poultry farm in the Amur and implement feed counterparties. Per hour of operation the company will be able to produce at least 15 tons of products. The plant has two elevators for 10 and 20 tons.

"Our products will in all regions of the Far East, as well as the regions of the Russian Federation. Researched this project, which will be supported by the budget, the Government of the Amur region" — said at an event to lay the first brick in the foundation businesses governor Oleg Kozhemyako.