Progress of the construction of the theater of opera and ballet in Vladivostok

Construction site was fenced by a high fence (December 2010)

Operate excavators (March 2011)

Mounted cranes. Formwork was raised to the ground (July 2011)

Builders of the Opera and Ballet Theater in Vladivostok ready for equipment installation stage

(October 2011)

Installation of metal facade (February 2012)

General view (March 2012)

Work in the auditorium

View from the bridge across the Golden Horn

The main staircase (April 2012)

Mechanical goes to all floors, nice work!

Ready to pit for a multi-level parking

Inside, too, "boiling" work

Theatre is becoming more finished look (May 2012)

The facade is covered with glass (July 2012)

Acoustics … (August 2012)

    Glass electrically. Icicles and snow on the roof will not be!

     

    The walls are fully tiled with granite and aluminum profile — it's decor. Originally planned from the tree, but then that takes into account a difficult climate Primorye, have decided to mount aluminum.

    In some areas of the theater served warm (December 2012)

    Since the project looks today. At the same time the preparation for landscaping around the theater, and work is underway inside the building.