Energy launched in Chelyabinsk 80 MVA substation

Residents of neighborhoods, located in the northwestern part of the city of Chelyabinsk, will consume power at the expense of a new substation "Krasnopolskaya."  The new substation is of strategic importance — it will provide electricity to one of the most promising and fastest growing areas of the city.

  • to date in the plans of developers - new housing in the area total area of 2 million square meters, and it is about 30,000 apartments, including neighborhood "The park"
  • to date in the plans of developers — new housing in the area total area of 2 million square meters, and it is about 30,000 apartments, including neighborhood "The park"

According to the general director of "IDGC of Urals" Valery Rodin, the total capacity installed at the substation transformers — 80 MVA.

Construction of "Krasnopolskaya" was implemented in the framework of the investment program of the Chelyabinsk region, aimed at the construction of new substations and upgrade existing ones. The cost of the project — 300 million, it will pay for itself within 8-9 years. In total for the five years of the program it is planned to invest about 9 billion rubles.

The service life of the substation without repair, the head of "IDGC of Urals" — about ten years, the basic equipment will last about 40 years.

"The substation pays for itself in eight to ten years, according to our calculations. Investment amount — 300 million rubles," — said Rodin.

 

In just the last five years in Chelyabinsk built three large power grid object. This substation "Kashirinskaya" which is loaded with the western part of the city, "massive", supplying the energy center, and "Granite" located in the Leninsky district.